329113 SOIL PREPARATION 1. Soiling, cultivating and grading 1.01 Earthwork is measured and given in accordance with the rules contained in section 031000 “Earthwork” of the method of measurement. 1.02 Planting soil is given in cubic meters as equal to the void filled after leveling to the depths shown in the detailed landscape drawings 1.03 Work is also deemed to include: - Marking boundaries of planting areas. - Applying fertilizers and herbicides to surfaces to receive filling. - Stockpiling and double handling of materials. - Cultivating and final grading on in situ topsoil filling. - Additional cultivation and application of herbicides during the liability period. - Prevention of erosion. 321440 STONE PAVING 1. Bases to pavings. 1.01 Excavation and filling are measured in cubic meters and given in accordance with the rules contained in section 031000 of the Method of Measurement. 1.02 Any fill/excavation required to match the paving required levels are covered under the unit pavers section