Hi Kenny and Ken: Please consider the tooling capacity of baffle and control board-small IMD: For baffle,we have 2 set of tooling already, the capacity is 1200 units Washer/day. .the tooling cost is about 21k$,lead time :75days.IF WE DO NOT START THE 3rd BACK-UP TOOLING RIGHT NOW,WE WILL NOT MEET THE MARKET REQUIREMENT IN FW52(11076 UNITS/WEEK)For small IMD(used in low end models), we only have one tooling, the capacity is 880 units/day. The tooling cost is about 146k$,lead time 90days. Please double check the SKU mix to decide whether we need to invest the back-up tooling. Because the appearance tooling should be paid by GEA, Please let us know you decision in this week.Best regardsGeorge