The implementation of each component is also uneven, implementation rate of component 1-4 is 16.64%, 24.6%, 29.27% and 35.7% respectively. The planned investment for 2021 is about RMB 675 million which accounts for 52% of total project budget approved at MTR, however, the completion rate till the end May was about 7.58%. The Bank’s disbursement system shows the disbursed loan amount is about USD 38.41 million and the disbursement rate is 25.61%. Comparing with last mission, project disbursement rate is increased by 7.73%.