(1). Determine the rated voltage according to the voltage level at the current transformer device <br>(2). Determine the CT primary rated voltage according to Ie = Igmax / 110% <br>(3). Determine the level group and wiring method according to the CT use of the transformer <br>(4). On the 100kV line side, set three sets of differential, overcurrent, and measurement CTs, and connect them into three-phase star <br>10kV main transformer outlets. Set up three sets of differential, measurement, measurement, and current protection CTs, and connect them into three-phase star <br>10kV Two groups of CTs for measurement, measurement and current protection are installed at the outlet of the load, and connected into a two-phase star <br>(5). Select the model and verify the thermal stability and dynamic stability according to the short circuit situation