Since December 21 Mr. Sacchettini leave, the company installed on December 26 and leave the work stoppage, the construction site is not much progress. The off-site November 25, 2019 to January 15, 2020, NEW progress described below: <br>. 1, KL710 / 711 furnace hood and complete the installation process; <br>2, PK720 / housing 721 and the installation efficiency filter <br>E401 / V401 hoisting apparatus main body, and this area is completed most of the steel; <br>3, factory workshops completed spacer plate, the upper shutter doors and windows installed; <br>4, office building renovation nearing completion, includes a ground floor office conditions.