We do not deny that the HLN line personnel have been able to meet the site requirements, but we are now equally concerned about the installation of HLQ line personnel arrangements. As far as the current personnel arrangements are in place, we do not see any HLQ line personnel information, and HLQ line TL25 equipment has arrived at the scene on April 15, TL10 will also arrive in Dalian port tomorrow (April 28), at the same time, according to Bruckner to our installation plan is also in early May to start the formal installation of equipment, but the staff arrangement is still zero progress! Please Bruckner can pay attention to our installation site personnel problems, do not sacrifice the interests of our Kanghui due to the needs of other customers, affecting our two sides have always been a good atmosphere of cooperation! !