Project implementation and disbursement status. Per project progress report prepared by PPMO, the cumulative completed project investment is about RMB 159.01 million, which is about 12.33% of total project budget. Project implementation has been increased by 5.32% since last mission. The implementation among project counties is imbalanced, detailed implementation status of the project and each county refer to table below.