(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 (Extension of time for Completion]; and(b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.