As now the purchased and arrived materials for suchtemporary power connection are arranged for the connection up to the CCB WWTP, modifyingthe power acquisition point would prolong the overall schedule of pumping houseconstruction. To maintain the connection point in WWPT, and also meanwhilereduce the influence to WWPT operation from that temp. power connection as muchas possible, we hope that we can use the P31ABHB66 cabinet, which is theincomer of capacitor bank panel, during the construction of new pumping house. Aslearned from relevant CEM personal, the CTs of this cabinet had been replacedto the larger size for adapting the installed cap. bank, and those CTs can satisfyfor the use of site construction. Moreover, the relevant connection measures donot need de-energization on the overall upstream busbar, while during the useof P31ABHB66, the respective cap. bank panel should be out-of-service temporarilyuntil the new pump house can be energized by its own power. To ensure theconstruction safety and the works can smoothly in line with the schedule, we hopethat CEM supervisors can permit us to use this P31ABHB66 cabinet for supplysite power during the construction pumping house.