The progress S-Curve shows the overall progress of the project as indicates in Chapter 2, item 2.1 Project Progress. For the month of March 2020, the actual worth of work done is 789.09 million Baht or 2.323% comparing with planned worth of work 1, 689. 18 million Baht or 4.971%.