Yesterday, we took out three filters from the 10 "LNG main line. This afternoon, we also completed the connection and leakage test of all the flanges. Therefore, we plan to start cleaning the 10 "LNG pipeline at 10:00 tomorrow morning, and then we need to introduce nitrogen from your mlng side to purge to tigergas side for water test. It is estimated that two days and two nights, please help us coordinate the cleaning work? If there is any problem, please let me know. thank you.<br>