If Ebusco accepts the bus like this, Ebusco will have a lot of work on the IT-System. The IT-Power KL15 could not be switched on. This causes that the IT could not be switched on for the FAT. Due to this a lot of IT parts could not be checked on functionality. Big Risk in Deurne on extra work on IT system due to, not connected components, missing cables, wrong wiring, wrong connections, finding cables.Missing parts need to be ordered in Deurne causing delay in deliver bus in time. Also a lot of IT parts were not installed, missing, not right installed. For the IT-Team this bus is not accepted on IT.