2.梁、板筋施工1.梁筋通常在梁底模支好后再进行绑扎,绑扎后经查无误后再进行侧模的支护,对于截面不高(≤500)的次梁可不受此影响,可将梁架的英语翻译

2.梁、板筋施工1.梁筋通常在梁底模支好后再进行绑扎,绑扎后经查无误后

2.梁、板筋施工1.梁筋通常在梁底模支好后再进行绑扎,绑扎后经查无误后再进行侧模的支护,对于截面不高(≤500)的次梁可不受此影响,可将梁架起绑扎,绑扎后再将梁筋落下。当梁纵向钢筋采用上下两层时,可采用在两层间垫以直径25mm的钢筋,以保持上下钢筋的排距,主次梁交接处应按设计要求加设吊筋及箍筋加密,箍筋的接头应交错布置在梁的两侧,接头位置应符合设计要求并相互错开。3.板筋应在梁筋绑扎完毕后施工,绑扎前在模板上按设计要求的规格在模板上划线。底层钢筋的弯钩应朝上,上层钢筋弯钩朝下并锚固在梁内。对于双层筋的板,应在上下层筋间加设脚撑,以保证两层筋的间距。4.在梁、板、柱的交汇处,往往钢筋较密,混凝土浇筑时下浆困难,绑扎时应量为混凝土浇筑创造条件,使钢筋间距至少留有30mm的间距,梁板筋绑扎后,应防止水电线管预埋时将钢筋抬高或压下,在混凝土浇筑前按要求加垫块。
0/5000
源语言: -
目标语言: -
结果 (英语) 1: [复制]
复制成功!
2. Beam and slab <br>reinforcement construction 1. Beam reinforcement is usually tied after the beam bottom formwork is supported. After lashing, the side formwork is supported after inspection. The secondary beams with low cross-section (≤500) are not required. For this effect, the beams can be set up and tied, and then the beam tendons can be dropped. When the longitudinal reinforcement of the beam adopts two upper and lower layers, a 25mm diameter steel bar can be used between the two layers to maintain the row spacing of the upper and lower steel bars. The main and secondary beams should be connected with lifting reinforcement and stirrup reinforcement according to the design requirements. The joints of the ribs should be staggered on both sides of the beam, and the joint positions should meet the design requirements and be staggered. <br>3. The slab reinforcement should be constructed after the beam reinforcement is tied up. Before lashing, mark the template on the template according to the specifications required by the design. The hooks of the bottom steel bars should face up, and the hooks of the upper steel bars should face down and be anchored in the beam. For slabs with double ribs, foot supports should be added between the upper and lower ribs to ensure the distance between the two ribs. <br>4. At the intersection of beams, slabs, and columns, the steel bars are often dense, and it is difficult to mortar during concrete pouring. When tying the concrete, the amount should be measured to create conditions for the concrete pouring, and the spacing between the steel bars should be at least 30mm. To prevent the steel bars from being raised or pressed down during the pre-embedding of water and electric wires, pad blocks should be added as required before concrete pouring.
正在翻译中..
结果 (英语) 2:[复制]
复制成功!
2. Beam, plate construction<br>1. Beam ribs are usually tied up after the beam bottom mold is well tied, tied after unsure and then side mold support, for the cross-section is not high (≤500) secondary beam can not be affected by this, the beam can be tied up, tied and then the beam ribs fall. When the beam vertical rebar adopts the upper and lower two layers, can be used in two layers between the pads with a diameter of 25mm of rebar, in order to maintain the rowing of the upper and lower rebar, the main secondary beam junction should be in accordance with the design requirements of the addition of lifting ribs and hoop encryption, the joints of the hoops should be staggered on both sides of the beam, the joint position should meet the design requirements and staggered with each other.<br>3. The ribs should be constructed after the beam ribs are tied, and the specifications of the design requirements are crossed on the template before the tie-up. The hook of the bottom rebar should be facing up, and the hook of the upper steel bar should be facing down and anchored in the beam. For double-layered ribs, foot support should be added between the upper and lower ribs to ensure the spacing of the two-layer ribs.<br>4. At the intersection of beams, plates and columns, often the rebar is denser, the concrete pouring is difficult, the amount of the concrete should be tied to create conditions for concrete pouring, so that the bar spacing at least 30mm spacing, the beam plate is tied, should prevent the water wire pipe pre-buried when the rebar is raised or pressed down, before concrete pouring according to the requirements of the pad block.
正在翻译中..
结果 (英语) 3:[复制]
复制成功!
Beam and slab reinforcement<br>1. The beam reinforcement is usually bound after the beam bottom formwork is supported, and the side formwork support can be carried out after the binding is checked to be correct. The secondary beam with low section (≤ 500) can not be affected by this. The beam can be lifted and bound, and the beam reinforcement can be dropped after binding. When the longitudinal reinforcement of beam adopts upper and lower layers, the reinforcement with diameter of 25 mm can be padded between the two layers to maintain the row spacing of upper and lower reinforcement. Hanging bars and stirrups shall be added at the junction of primary and secondary beams according to the design requirements. The joints of stirrups shall be staggered on both sides of the beam, and the joint position shall meet the design requirements and be staggered.<br>3. The plate reinforcement shall be constructed after the beam reinforcement is bound, and the line shall be drawn on the formwork according to the design requirements before binding. The hook of bottom reinforcement shall face upward, and the hook of upper reinforcement shall face downward and be anchored in the beam. For the slab with double-layer reinforcement, the foot brace should be added between the upper and lower reinforcement to ensure the spacing between the two layers of reinforcement.<br>4. At the intersection of beam, slab and column, the reinforcement is often dense, and it is difficult to pour the concrete during concrete pouring. During the binding, it is necessary to create conditions for concrete pouring, so that the spacing of steel bars is at least 30mm. After the binding of beam and slab reinforcement, it is necessary to prevent the reinforcement from being raised or pressed down when the water and electricity pipelines are embedded. Cushion blocks shall be added before concrete pouring.<br>
正在翻译中..
 
其它语言
本翻译工具支持: 世界语, 丹麦语, 乌克兰语, 乌兹别克语, 乌尔都语, 亚美尼亚语, 伊博语, 俄语, 保加利亚语, 信德语, 修纳语, 僧伽罗语, 克林贡语, 克罗地亚语, 冰岛语, 加利西亚语, 加泰罗尼亚语, 匈牙利语, 南非祖鲁语, 南非科萨语, 卡纳达语, 卢旺达语, 卢森堡语, 印地语, 印尼巽他语, 印尼爪哇语, 印尼语, 古吉拉特语, 吉尔吉斯语, 哈萨克语, 土库曼语, 土耳其语, 塔吉克语, 塞尔维亚语, 塞索托语, 夏威夷语, 奥利亚语, 威尔士语, 孟加拉语, 宿务语, 尼泊尔语, 巴斯克语, 布尔语(南非荷兰语), 希伯来语, 希腊语, 库尔德语, 弗里西语, 德语, 意大利语, 意第绪语, 拉丁语, 拉脱维亚语, 挪威语, 捷克语, 斯洛伐克语, 斯洛文尼亚语, 斯瓦希里语, 旁遮普语, 日语, 普什图语, 格鲁吉亚语, 毛利语, 法语, 波兰语, 波斯尼亚语, 波斯语, 泰卢固语, 泰米尔语, 泰语, 海地克里奥尔语, 爱尔兰语, 爱沙尼亚语, 瑞典语, 白俄罗斯语, 科西嘉语, 立陶宛语, 简体中文, 索马里语, 繁体中文, 约鲁巴语, 维吾尔语, 缅甸语, 罗马尼亚语, 老挝语, 自动识别, 芬兰语, 苏格兰盖尔语, 苗语, 英语, 荷兰语, 菲律宾语, 萨摩亚语, 葡萄牙语, 蒙古语, 西班牙语, 豪萨语, 越南语, 阿塞拜疆语, 阿姆哈拉语, 阿尔巴尼亚语, 阿拉伯语, 鞑靼语, 韩语, 马其顿语, 马尔加什语, 马拉地语, 马拉雅拉姆语, 马来语, 马耳他语, 高棉语, 齐切瓦语, 等语言的翻译.

Copyright ©2024 I Love Translation. All reserved.

E-mail: